Update - 6/30/16
The work proposed for the week of July 4th includes:
- West Side Streets
- Fellows Street – Utility structure work is to continue.
- S. 6th Street - Utility structure work is to continue. Water main installation is scheduled to begin between McKinley and Horne Streets.
- S. 15th Street - Saw cutting of concrete and pavement is planned.
- Ash Street - Saw cutting of concrete and pavement is planned.
- Pine Street - Saw cutting of concrete and pavement is planned.
- East Side Streets
- Highgate Course Area – Saw cutting of concrete or pavement may begin.
- Industrial Drive - Saw cutting of concrete or pavement may begin.
- Kautz Road - Saw cutting of concrete or pavement may begin.
- Van Buren Avenue - Saw cutting of pavement may begin.