Update - 7/21/16

The work proposed for the week of July 25th includes:

  • Resurfacing Area (Division Street to Cambridge Drive) - No work anticipated.
  • Reconstruction Area (Cambridge Drive to Tyler Road) – The contractor will be placing the first layer of roadway pavement, replacing the remaining driveway aprons and removing the remaining sidewalk to be repaired.  The roadway in this area will continue to be closed to traffic.  Once the first layer of asphalt has been placed those homes who already have driveway aprons replaced may park in your driveway for the duration of the project.  The only driveways yet to replace in this area are the asphalt driveways, which will be replaced shortly after the first layer of asphalt.  Once the asphalt driveways are installed access will be allowed that same day.

 