Update - 6/4/21

Anticipated construction work for the week of June 7-11

Please Note: All work contingent on weather

  • East Side Streets
    • Fox Glen Drive – Asphalt removal and replacement may begin.
    • Fairfax Road – Asphalt removal and replacement may begin.
    • Forest Ridge Road – Asphalt removal and replacement may begin.
    • Hunt Club Drive – Asphalt removal and replacement may begin.
    • S. 11th Avenue – Asphalt removal and replacement may begin.
    • S. 12th Avenue- Watermain work continuing.
    • S. 13th Avenue – Continue underground utility. Remaining concrete pours may begin.
    • Jewel Avenue – Asphalt removal and replacement may begin.
    • Jay Lane – Asphalt removal and replacement may begin.
  • West Side Streets
    • Renaux Blvd. – Asphalt replacement may begin.
    • St. Germain Place – Asphalt replacement may begin.
    • Oak Street – Asphalt replacement may begin.
    • N. 5th Street – Continue underground utility. Remaining concrete pours may begin.