Update - 5/3/24

Fox Glen Dr Area (Fox Glen Dr, Fox Glen Ct, Glenbriar Dr, Glenbriar Ct, and Glen Eagles Ct)

  • This week, the contractor completed concrete removals and replacements in the area.
  • Brick paver restoration is expected to begin today and be completed early next week.
  • Next week, milling is expected to begin on Monday, 5/6 (weather permitting) and paving is expected to begin towards the end of the week.

Forest Ridge/Huntington Area (Forest Ridge Rd, Huntington Rd, Essex Ct, Sterling Ct, and Foxhill Ct)

  • Next week, concrete removals and replacements are expected to begin and be completed by the end of the week. Residents who will have impacts to driveway access will receive a door hanger with additional information regarding parking arrangements.
  • Water service utility work is expected to begin today and continue next week. Affected residents will be notified in-person by the contractor in advance before water is temporarily shut-off to the house and service is restored.
  • Next week, watermain valve replacements are expected to begin and residents will be notified by door tags in advance of scheduled shut-downs. Door tags will include additional information regarding the shut-down.

Royal Fox Area (Royal Fox Dr, Royal Fox Ct, Royal Troon Ct, Royal Lytham Dr, Royal Lytham Ct, Turnberry Rd, Royal Kings Ct, Royal Queens Ct, Royal Ashdown Ct)

  • Saw-cutting began this week and is expected to continue next week.

Royal Kings Area (King Edward Ave, King James Ave, King Alford Ct, King Williams Ct, King Richard Ct, King James Ct, Queen Anne Ct, King Henry Ln, King Charles Ln, King George Ln)

  • Saw-cutting is expected to begin next week.