Week of July 7, 2014
Phase One utility repairs are being completed on Ash Street and Ohio Avenue, and are planned for McKinley Street this week.
Phase Two curb and sidewalk repairs are in progress on Foxfield Drive and Lakeside Drive this week.
Phase One utility repairs are being completed on Ash Street and Ohio Avenue, and are planned for McKinley Street this week.
Phase Two curb and sidewalk repairs are in progress on Foxfield Drive and Lakeside Drive this week.
The Municipal Building Parking Lot Construction Project was approved at the July 7, 2014 City Council Meeting.
Construction is expected to begin the week of July 14, 2014.
The Tyler Road Pavement Resurfacing Project has been awarded to Geneva Construction Company, Aurora, IL. The limits of this project are from East Main Street to Kirk Road. The placing of traffic control is scheduled to begin on Monday July 7, with the start of construction planned for Monday July 14.
Phase One utility repairs have been completed on Squire Lane, Foxfield Drive, Frontage Road, Kehoe Street, Alice Court and Margaret Court, and are in progress on Ash Street, McKinley Street and Ohio Avenue this week.
Phase One utility repairs are continuing on Squire Lane, Foxfield Drive, Frontage Road, Kehoe Street, Alice Court, Margaret Court and Ash Street.
Utility repairs are planned to begin on Ohio Avenue and McKinley Street this week.
Phase One utility repairs have been completed in Cambridge East neighborhood, and have started on Squire Lane, Foxfifeld Drive, Frontage Road, Kehoe Street, Alice Court and Margaret Court. Utility repairs are planned to begin on McKinley Street this week.
The main section of the biosolids and operational building is now completed. This section houses liquid storage, chemical storage, pumping and dewatering equipment along with the new Motor Control Center and plant power distribution. Equipment has been through start-up procedures with staff training. Most equipment is now operational and running on a daily basis.
Water main installation, hydrant replacements, water service connections, testing and restoration of the parkway have been completed on South 19th Street & Walnut Drive Water Main Improvement Project.
Phase One utility repairs have started on Cambridge Drive, Cambridge Court, Jeanette Avenue, Midway Avenue and Cumberland Green Drive as of May 30.
The 2014 MFT Street Rehabilitation Project has been awarded to Hardin Paving Services, from Hillside, Illinois.
Phase One utility repairs are anticipated to begin on Cambridge Drive, Cambridge Court, Jeanette Avenue, Midway Avenue and Cumberland Green Drive on Tuesday, May 27, 2014.
The MFT Project will include Hot Mix Asphalt pavement removal and replacement, curb and sidewalk repairs, public utility repairs, parkway restoration, and other appurtenant work for a complete improvement.