Construction, Road

Update 5/5/22

Anticipated work for the week of 5/9 - 5/13/22 

Millington - Fire hydrant removal and replacement as well as various utility work.  Residents will be notified with a door hanger if they will be impacted by shut downs. 

Update 5/5/22

Anticipated work for the week of 5/9 - 5/13/22

  • Utility work - dig and prepare for valve replacement.  In the event of shut downs, residents will be notified with door hangers
     
  • Storm sewer removal and replacement

Update - 4/28/22

Anticipated work for the month of May: 

  • Concrete curbs and sidewalks will be completed starting May 4th
  • Landscaping restoration will begin the week of May 9th 
  • Pavement restoration is scheduled to take place May 13th to May 20th

Update 3/11/22

The contractor will be moving East across South 17th St. on 3/11/2022.  In order to complete this work, South 17th St. will be closed for the majority of the business day at the Walnut St. intersection.