Update - 6/1/23
Anticipated construction work for the week of June 4 – June 10
Please Note: All work contingent on weather
East Side Streets
East Side Streets
Mother nature has given the gift of very good construction weather and this week lots of progress was made toward completing the demolition portion of the project. Removal of the walls and ramps to the river walk is in progress and crews have completed a substantial portion of the demolition work which means it’s almost time to start building! Keep checking for updates as we are anticipating starting on building foundations to support the new plaza features in the near future.
Please Note: All work contingent on weather
East Side Streets
Demolition of the existing South 1st Street concrete paving is complete! Removal of the concrete paving, sidewalks, planter boxes and other items from Main Street to Walnut Street has been completed and crews are moving on to sidewalks, bricks and planters on the east side of the road with plans to start the demolition process on the existing river walk ramp next. A reminder that this area is a construction zone and not open to the public. However, please enjoy the process and views from behind the construction fence and keep up with our progress toward this exciting new feature in the h
East Side Streets
Anticipated construction for the week of May 15 - May 19
Please Note: All work contingent on weather
This week work continues on the site investigation and construction fencing/site containment phase of the project. Installation of additional signage, fencing and other pedestrian/traffic control features will be installed and work will begin on removal and salvage of brick pavers from both the existing east plaza and the roadway bricks for future use on this project and throughout the City. Mobilization of steel and other materials for the new pedestrian ramp is expected in the next 7 to 10 days and demolition of the existing hardscapes (sidewalks, street and planters) is anticipate
Anticipated construction work for the week of May 8 - May 12
Please note: All work contingent on weather
The second phase of the 1st Street Plaza Expansion project kicks off today (May 1, 2023) with the project contractor Martam Construction of Elgin, Illinois beginning to mobilized equipment and material to the site. Construction fencing and pedestrian/traffic control will commence this week, followed shortly after by utility investigation and demolition of the existing street and sidewalks.