Next week the contractor will perform the following:
Adams Ave/Ct: Concrete removal and replacements to continue. Utility repairs to continue. Asphalt removal and replacement may begin.
Dover Hill Ct: Concrete removal and replacements to begin. Utility repairs to begin. Asphalt removal and replacement may begin.
Fox Chase Dr: Asphalt removal and replacement to continue.
Jackson Ave: Concrete removal and replacements to begin. Asphalt removal and replacement may begin.
Jewel Ave: Asphalt removal and replacement to begin.
N. 12th Ave: Asphalt removal and replacement to begin.
Mildred Ave: Asphalt removal and replacement to continue.
Persimmon Dr: Concrete removal and replacements to begin.
Rita Ave: Asphalt removal and replacement to continue.
Ronzheimer Ave: Asphalt removal and replacement to continue.
Ruth Ave: Asphalt removal and replacement to begin.
Spring Ave: Concrete removal and replacements to begin. Asphalt removal and replacement may begin.