Anticipated construction work for the week of June 29- July 2
Please Note: All work contingent on weather
No work scheduled for Friday July 3rd
East Side Streets
- N. 2nd Ave. โ No work at this time
- Edward Ave. โ Utility repair work including a water main shutdown, curb and sidewalk removal and replacement, landscape restoration
- Fox Glen Dr. โ Curb and sidewalk removal and replacement, landscape restoration
- King Richard Circle โ Curb and sidewalk removal and replacement, landscape restoration
- Queen Elizabeth Ct. - Curb and sidewalk removal and replacement, landscape restoration
- Pinelands Rd. - No work at this time
West Side Streets
- Fairview Dr. - No work at this time
- Heritage St./Ct. - Curb and sidewalk removal and replacement, landscape restoration
- Horne St. โ Utility repair work
- Killdeer Ln. โ Landscape restoration
- S. 12th St. - No work at this time
- S. 19th Street โ No work at this time
- Tradition Blvd. โ Curb and sidewalk removal and replacement, landscape restoration