Anticipated construction work for the week of June 29- July 2
Please Note: All work contingent on weather
No work scheduled for Friday July 3rd
East Side Streets
- N. 2nd Ave. – No work at this time
- Edward Ave. – Utility repair work including a water main shutdown, curb and sidewalk removal and replacement, landscape restoration
- Fox Glen Dr. – Curb and sidewalk removal and replacement, landscape restoration
- King Richard Circle – Curb and sidewalk removal and replacement, landscape restoration
- Queen Elizabeth Ct. - Curb and sidewalk removal and replacement, landscape restoration
- Pinelands Rd. - No work at this time
West Side Streets
- Fairview Dr. - No work at this time
- Heritage St./Ct. - Curb and sidewalk removal and replacement, landscape restoration
- Horne St. – Utility repair work
- Killdeer Ln. – Landscape restoration
- S. 12th St. - No work at this time
- S. 19th Street – No work at this time
- Tradition Blvd. – Curb and sidewalk removal and replacement, landscape restoration