Anticipated construction work for the week of July 16 – July 22
Please Note: All work contingent on weather, street access will be maintained during asphalt milling.
East Side Streets
- Fox Chase Blvd. – Landscape restoration, potential asphalt milling
- Hampton Course – Landscape restoration
- Lexington Ave. – Final watermain connection. Valve and hydrant replacements. Scheduled water shutdown for Monday 7/17. Concrete restoration to begin.
- Lancaster Ave. – Concrete restoration to begin
- Liberty Ave. – Concrete restoration to begin
- Liberty Ct. – Concrete restoration to begin
- Cranbrook Ave. – Concrete restoration to begin
West Side Streets
- River View Dr. – Asphalt milling, driveway repairs
- River Ridge Dr. – Asphalt milling, driveway repairs
- Prairie Crossing Dr. – Asphalt milling, driveway repairs
- Renard Ln. – Asphalt milling, driveway repairs
- Voltaire Ln. – Asphalt milling, driveway repairs
- Provence Dr./Ct. – Asphalt milling, driveway repairs
- Antoine Pl./Ct. – Asphalt milling, driveway repairs