Update - 5/24/24

Fox Glen Dr Area (Fox Glen Dr, Fox Glen Ct, Glenbriar Dr, Glenbriar Ct, and Glen Eagles Ct)

  • This week, the contractor completed paving in the area.

Forest Ridge/Huntington Area (Forest Ridge Rd, Huntington Rd, Essex Ct, Sterling Ct, and Foxhill Ct)

  • This week, the majority of damaged asphalt driveways were repaired, landscape restoration work was completed, and the majority of remaining concrete replacement work was completed. Additionally, brick paver restoration work began and is expected to continue next week.
  • Next week, milling is expected to begin on Tuesday, May 28. The pavement on Forest Ridge Rd and Huntington Rd will be removed down to the stone (~4 inches) and temporary stone ramps will be constructed by the contractor for each driveway and onto connecting streets to maintain access. Following the completion of milling in the area, Forest Ridge Rd and Huntington Rd will receive a heavy application of oil overnight (expected on Wednesday night into Thursday morning), between the hours of 12 am โ€“ 5 am. The City asks that residents avoid driving on these two roads between those times in order to allow the oil to cure and minimize the tracking onto vehicles and the surrounding pavement. The contractor will do their best to keep noise to a minimum during the oil application process; however, residents are advised that the truck back-up alarm will be audible when needed for maneuvering. Paving is expected to begin on Thursday, May 30 and be completed by the end of the week.

Royal Fox Area (Royal Fox Dr, Royal Fox Ct, Royal Troon Ct, Royal Lytham Dr, Royal Lytham Ct, Turnberry Rd, Royal Kings Ct, Royal Queens Ct, Royal Ashdown Ct)

  • This week, the contractor began watermain valve replacement work and replacements are expected to continue next week. Residents will be notified by door tags in advance of scheduled shut-downs. Door tags will include additional information regarding the shut-down.
  • Concrete removals & replacements have temporarily paused for the area on the West side of Kirk Rd. Residents who will have impacts to driveway access will receive a door hanger with additional information regarding parking arrangements in advance before work restarts.
  • Next week, for the area on the West side of Kirk Rd, utility structure adjustment/replacement work is expected to begin.
  • Next week, for the area on the East side of Kirk Rd, landscape restoration work is expected to begin early in the week and milling is expected to begin towards the end of the week.

Kings Area (King Edward Ave, King James Ave, King Alford Ct, King Williams Ct, King Richard Ct, King James Ct, Queen Anne Ct, King Henry Ln, King Charles Ln, King George Ln)

This week, utility structure adjustment/replacement work began and is expected to continue next week.