- The main staircase is in place and the concrete is being poured today.
- The flooring is ongoing, with the majority of the second floor complete and the first floor being prepped.
- The Main lobby efforts are focused on final framing of the soffits and the last few pieces of glass that were field measured earlier this week.
- The stoops at all of the exterior doors have had the outside frames poured and will be completed early next week when the sally port garage floor is poured.
- The pond at the west side of the building is almost complete and will kick off the start of landscaping work. Specifically the seeding at that area.