- Curb and gutter started yesterday and they completed an impressive amount of work in one day. We held off a few areas to keep the appropriate amount of access for the other trades and are planning to bring them back when we can knock out the sidewalks as well.
- The main staircase pour went well last week and we are now moving the construction traffic to that staircase while the others are being completed with framing, insulation, and finishes.
- The Sally Port and support garage along with the north section of the squad garage are prepped to be poured next week Tuesday which will help move a lot of the equipment and material out of the main lobby. This will help keep the finish trades moving efficiently and safely.
- The exterior seat walls are framed and prepped for being poured today.
- The detention area is nearing the finish with all the benches poured, block infill started, and the pick proof caulk installed.