Work anticipated week of 8/9/21
Please note all work is weather dependent
Remove 9th Ave. culvert
Begin retaining wall installation along the north and south sides of Illinois Ave.
Final grading and haul off in area north of Illinois Ave. Install stone toe armoring along the banks.
Excavate and begin framing and placing rebar for bridge abutments
Potentially pave bike path from Indiana to Illinois