Anticipated work for the week of 8/30
* Please note - all work is weather dependent
Grading and place stone for bicycle path and sidewalk north of Illinois
Set the pedestrian bridge at the north project limit and pour the concrete deck and approaches
Pour curb and gutter on Illinois Avenue
Final grading and top soil placement