- Thursday, October 27 - Broken Curb is being removed.
- Friday, October 28 - Curb replacement and Target entrance removal - North Target entrance will be closed October 28 to November 8
- Friday/Saturday, October 28 and 29 - Grading in the IL Dept. of Transportation Right-of-Way; work will continue into the week of October 31
- Friday/Saturday, October 28 and October 29 - Base preparation
- Monday, October 31 - Pour concrete, including Target North Access Ramp
- Monday, October 31 - the sanitary manhole in Ohio Avenue is going to be adjusted. The wet concrete and need to cure is going to cause a closure of Ohio Avenue for at least one day.
- Wednesday, November 2 - Asphalt work will be completed
- Friday, November 4 - Pour concrete on Kautz Road - curing will last until November 8
- Preparation for pouring sidewalks in IL Dept. of Transportation Right-of-Way; no exact date for the pour