Update - 7/19/24

Kings Area (King Edward Ave, King James Ave, King Alford Ct, King Williams Ct, King Richard Ct, King James Ct, Queen Anne Ct, King Henry Ln, King Charles Ln, King George Ln)

  • This week, the contractor completed patching and began placing asphalt level binder
  • Next week, the contractor is expected to complete level binder and adjust drainage structures that are in the roadway

Division St Area (Walnut Hill Ave, Patricia Ln, Via Veneto Dr, Chandler Ave)

  • This week, the contractor completed landscape restoration and driveway repairs and began pavement removal
  • Next week, the contractor will mill pavement on Patricia and Walnut Hill. They will perform base reclamation on Chandler and Via Veneto on Monday 7/22. The contractor will place asphalt binder and surface on all roads.

Abbeywood & Meadow Area (Abbeywood Dr, Easton Pl, Pendleton Ct, Brittany Ct, Thornhill Farm Rd, Green Willow Ln, Kensington Pl, Edgewild Ct, Meadow Dr, Crane Rd)

  • This week, the contractor completed concrete restoration throughout the neighborhood and continued utility work and cleanup
  • Next week, the contractor is expected to complete utility work and begin landscape restoration.

Harvest Hills & Renaux Manor Area (Raphael Ct, Red Rose Dr, St Michel Ct, St Michel Ln, Hillsboro Ct, Grand Ridge Rd, Fairmont Ct, Sunbury Dr, Fairhaven Dr, Valley View Dr, Springfield Way, Red Sky Dr, Horizon Dr W, Langston Cir)

  • Next week, concrete removal and replacement is expected to begin on Tuesday 7/23
created Jul 19, 2024 updated Jul 19, 2024