Update - 7/29/24

Kings Area (King Edward Ave, King James Ave, King Alford Ct, King Williams Ct, King Richard Ct, King James Ct, Queen Anne Ct, King Henry Ln, King Charles Ln, King George Ln)

  • This week, the contractor completed placing level binder and began placing the final asphalt surface layer.
  • Next week, the contractor is expected to complete placing the final asphalt surface layer.

Division St Area (Walnut Hill Ave, Patricia Ln, Via Veneto Dr, Chandler Ave)

  • This week, the contractor completed milling, base reclamation, and paved the first asphalt layer on all the roads. The final asphalt layer has been completed on Walnut Hill Ave and Patricia Ln.
  • Next week, the contractor is expected to complete placing the final asphalt surface layer on Via Veneto Dr and Chandler Ave.

Abbeywood & Meadow Area (Abbeywood Dr, Easton Pl, Pendleton Ct, Brittany Ct, Thornhill Farm Rd, Green Willow Ln, Kensington Pl, Edgewild Ct, Meadow Dr, Crane Rd)

  • This week, the contractor completed landscape restoration work.
  • Next week, the contractor is expected to begin asphalt milling.

Harvest Hills & Renaux Manor Area (Raphael Ct, Red Rose Dr, St Michel Ct, St Michel Ln, Hillsboro Ct, Grand Ridge Rd, Fairmont Ct, Sunbury Dr, Fairhaven Dr, Valley View Dr, Springfield Way, Red Sky Dr, Horizon Dr W, Langston Cir)

  • Next week, concrete removals and replacements are expected to begin on 7/31. Residents who will have impacts to driveway access will receive a door hanger with additional information regarding parking arrangements.