The City of St. Charles is pleased to inform you that new Sanitary and Strom Sewer will be installed on Indiana Street from S. 17 Street to S. 13 Street.

CONTRACTOR AND INSPECTOR:

The contract for this work has been awarded to J & S Construction of Oswego, IL. Fehr Graham, Inc. will be the on-site engineer performing construction inspections and acting as the field liaison to residents and property owners.  Any questions or concerns may be directed to City of St Charles Public Works at (630) 377-4405.

START DATES & COMPLETION DATES:

We are working with the contractor to determine the exact dates, but generally anticipate construction to occur as follows:

  • Sanitary and Storm Sewer Line Construction – June 3rd – August 1st
  • Concrete and Asphalt Restoration – August 1st – August 23rd
  • Landscaping & Final Restoration – August 23rd – September 6th
  • Project Completion Date – September 9th

Please visit the Public Improvements Project page on the City’s website at www.stcharlesil.gov/projects for information on the start dates and construction updates for each street. 

IMPROVEMENTS & PROCESS

This project has been divided into three phases to facilitate the completion of the project in a timely manner and with as little disruption to residents and properties as possible:

  • Phase I: Sanitary and Storm Line construction includes removal of sections of the roadway, some driveway approaches, roadway parking, curb, and sidewalks. During this phase, the site engineer and the City will provide notification to the impacted home, apartment or business.  Please relocate your cars to available parking areas or adjacent side streets by 7:00 AM. Access can resume when the barricades are removed from your driveway or roadway.

The project will require some water shutdowns. The City will be coordinating scheduled water shutoffs with impacted customers as part of this project. This will include a door notification of the expected shut down time and dates. The City will make every effort to schedule all water main shutdowns.

  • Phase IIIThe third phase will involve parkway restoration.  All areas disturbed by construction will be restored. A recommended seed maintenance and watering schedule will be available on the project website.

Due to the scope, complexity, and nature of this work, as well as the unpredictability of weather, some delays and disruptions may occur.  There may be times when no work is occurring on your street. We ask for your understanding during these times; work is being coordinated and anticipated to be finished by the completion date of September 9th.  All work is weather dependent.

PUBLIC RIGHT-OF-WAY:

Please note that all work will be performed within the City right-of-way.  If you have any type of existing features within the City right-of-way area (i.e. sprinkler system, landscape features, special decorative rocks, brick driveways, electronic “invisible” dog fence, etc.), precautions should be taken by you, the homeowner, to remove or store these items right away to assure that they are not damaged. The City will not repair or replace private appurtenances left within the City right-of-way.

MAIL & GARBAGE SERVICE:

Mail and Garbage service will not be interrupted during construction.  Please leave your garbage at the end of your driveway on your normally scheduled pick up day by 6 am as pick may occur earlier than normal to avoid the construction work.

PROJECT WEBSITE:

Updates regarding this project can be found on the City’s website at www.stcharlesil.gov/projects.  Look for the Walnut Street Water Main Replacement & Storm Sewer Improvement Project.  The City will be adding project updates weekly upon commencement of construction.

Update - 6/25/24

The Indiana and 14th Street Project continues to move along. For the rest of this week and into early next week, Indiana Street will be closed between S. 17th and S. 14th during normal business hours of 7am – 5pm.

Update - 6/11/24

The project on the Indiana and 14th Street continues to move along. For the rest of this week into early next week. Indiana Street will be closed during the normal business hours of 7am – 5pm. This crew will be moving into the intersection of Indiana and S 14th Street.