Update - 6/25/24
The Indiana and 14th Street Project continues to move along. For the rest of this week and into early next week, Indiana Street will be closed between S. 17th and S. 14th during normal business hours of 7am – 5pm.
The City of St. Charles is pleased to inform you that new Sanitary and Strom Sewer will be installed on Indiana Street from S. 17 Street to S. 13 Street.
CONTRACTOR AND INSPECTOR:
The contract for this work has been awarded to J & S Construction of Oswego, IL. Fehr Graham, Inc. will be the on-site engineer performing construction inspections and acting as the field liaison to residents and property owners. Any questions or concerns may be directed to City of St Charles Public Works at (630) 377-4405.
START DATES & COMPLETION DATES:
We are working with the contractor to determine the exact dates, but generally anticipate construction to occur as follows:
Please visit the Public Improvements Project page on the City’s website at www.stcharlesil.gov/projects for information on the start dates and construction updates for each street.
IMPROVEMENTS & PROCESS
This project has been divided into three phases to facilitate the completion of the project in a timely manner and with as little disruption to residents and properties as possible:
The project will require some water shutdowns. The City will be coordinating scheduled water shutoffs with impacted customers as part of this project. This will include a door notification of the expected shut down time and dates. The City will make every effort to schedule all water main shutdowns.
Due to the scope, complexity, and nature of this work, as well as the unpredictability of weather, some delays and disruptions may occur. There may be times when no work is occurring on your street. We ask for your understanding during these times; work is being coordinated and anticipated to be finished by the completion date of September 9th. All work is weather dependent.
PUBLIC RIGHT-OF-WAY:
Please note that all work will be performed within the City right-of-way. If you have any type of existing features within the City right-of-way area (i.e. sprinkler system, landscape features, special decorative rocks, brick driveways, electronic “invisible” dog fence, etc.), precautions should be taken by you, the homeowner, to remove or store these items right away to assure that they are not damaged. The City will not repair or replace private appurtenances left within the City right-of-way.
MAIL & GARBAGE SERVICE:
Mail and Garbage service will not be interrupted during construction. Please leave your garbage at the end of your driveway on your normally scheduled pick up day by 6 am as pick may occur earlier than normal to avoid the construction work.
PROJECT WEBSITE:
Updates regarding this project can be found on the City’s website at www.stcharlesil.gov/projects. Look for the Walnut Street Water Main Replacement & Storm Sewer Improvement Project. The City will be adding project updates weekly upon commencement of construction.
The Indiana and 14th Street Project continues to move along. For the rest of this week and into early next week, Indiana Street will be closed between S. 17th and S. 14th during normal business hours of 7am – 5pm.
Next week sanitary and stormwater construction on the Indiana Street and S. 14th Street will continue.
The project on the Indiana and 14th Street continues to move along. For the rest of this week into early next week. Indiana Street will be closed during the normal business hours of 7am – 5pm. This crew will be moving into the intersection of Indiana and S 14th Street.