The City is performing standard maintenance on the Prairie Street Bridge.

Project Phase: Construction
Proposed Improvements: Concrete repairs and deck patching, epoxy crack injection, protective coat application, cleaning scuppers and expansion joints, cleaning and painting exposed rebar, removal and replacement of sidewalk inlays.
Contractor:  MYS Incorporated
Construction Engineer:  Rick Fox, P
hone: 630-816-0766, Email: rfox@benesch.com
Estimated Timeline:  July 8, 2024 – August 9, 2024
Project Locations:  Prairie Street bridge over the Fox River
Road Closures:  The Prairie Street bridge will be closed to vehicles and pedestrians for the duration of the project. All traffic will be detoured to the Illinois Street bridge.

 