Update - 9/30/20
The contractor will be completing the installation of all underground utilities this week. The concrete and asphalt schedule, weather pending, is as follows:
Update - 9/21/20
Punchlist work is ongoing
Update - 8/19/20
Please Note:Â Project has reached substantial completion at this time.
All Streets
- Punchlist repair work and cleanup
Update - 08/13/20
Please Note: All work contingent on weather
East Side Streets
- N. 2nd Ave. – No work at this time
- Edward Ave. – No work at this time
- Fox Glen Dr. – No work at this time
- King Richard Circle – No work at this time
- Queen Elizabeth Ct. - No work at this time
- Pinelands Rd. - No work at this time
West Side Streets
Update 7/20/20
This week the contractor will directional drill the water main along the north leg of 2nd Avenue, and will begin preparing for the watermain installation along Delnor Avenue.
Update - 7/16/20
Please Note: All work contingent on weather
- Punchlist repair work and cleanup
Update - 7/16/20
Please Note: All work contingent on weather
East Side Streets
- N. 2nd Ave. – No work at this time
- Edward Ave. – Landscape restoration
- Fox Glen Dr. – Landscape restoration, asphalt surface
- King Richard Circle – Landscape restoration
- Queen Elizabeth Ct. - Landscape restoration
- Pinelands Rd. - No work at this time
West Side Streets
Update - 07/10/20
Next week the contractor will directional drill the water main along the south leg of 2nd Avenue, and may begin the installation of the watermain along the north leg of 2nd Avenue.Â
Update - 07/09/20
Please Note: All work contingent on weather
- Asphalt surfacing