7/5/19 Update
- The garage ADA ramp has been poured which means we can now start to move trades out of that space to prep for the epoxy.
- The detention fixtures are being installed and the specialty plank ceilings are in the final stages of completion.
- The storm shelter shrouds are installed as I mentioned above.
- These cover the 90 degree bends that all of the mechanical piping coming into the storm shelter makes.