Update - 5/30/19
Next week the contractor will complete the replacement of asphalt driveway aprons. Roadway base reclamation and paving is tentatively scheduled for the week of June 10th.
Next week the contractor will complete the replacement of asphalt driveway aprons. Roadway base reclamation and paving is tentatively scheduled for the week of June 10th.
Anticipated construction work for the week of June 3-7
East Side Streets
West Side Streets
The wet May weather has been less than ideal for open trench excavation, and particularly for the replacement of a storm water conveyance system. While awaiting favorable conditions, City staff has been working closely with our consultant engineer and contractor to address utility conflicts through routing modifications of the storm sewer. At this point, construction is tentatively scheduled to begin June 3.
Next week the contractor will be performing the following activities:
Road Closure Alert: Edward Avenue will be closed on Thursday, May 30th near the intersection of Nicholas Avenue. The closure is anticipated to begin at 8 AM and remain until 5 PM.
Next week the contractor will continue replacing the north/east side curb and gutter.
Anticipated construction work for the week of May 27-231
East Side Streets
West Side Streets
Next week the contractor will be performing the following activities:
Next week the contractor will be replacing the south/west side curb and gutter. Weather pending, residents are anticipated to have driveway access restored for Memorial Day weekend.
Anticipated construction work for the week of May 20-24
East Side Streets
West Side Streets
1. The main staircase stingers (sides) are in and the pans have been placed.
2. The main vestibule glass wall framing is installed and ready for glass.
3. The first floor lobby drywall has started with the south wall complete.
4. The men’s locker room and workout room flooring is complete.
5. The detention benches have been formed.