You are here

Project News

Update 9/2/2016

The paving work has been completed at all locations.  The contractor will continue placing the topsoil in areas where the parkways have been disturbed over the next week or so.  Sod restoration to take place in early September.  In addition the contractor will be working on any outstanding punch list items over the next few weeks.  

Update - 8/26/16

The Illinois Bridge Repair project is starting to wrap up.  The contractor will be making a change to the traffic pattern on Monday, August 29th.  The bridge will be fully open to traffic by the end of the day, with a temporary lane closure next week to complete some punch list items.  Two way traffic will be maintained through the duration of the project.

Update - 8/25/16

The Illinois Bridge Repair project is starting to wrap up.  The contractor will be making a change to the traffic pattern on Friday, August 26th.  The bridge will be fully open to traffic by the end of the day, with a temporary lane closure next week to complete some punch list items.  Two way traffic will be maintained through the duration of the project.

Update - 8/19/16

The contractor has completed the paving work.  Over the next week or so the contractor will work on any outstanding punch list items.  The placement of the sod restoration is anticipated in early September.

Pages